F23 Bicycle highway

Canal route North

Start

08/2019

End

09/2024

Status

In progress

The ‘Werken aan de Ring’ programme aims to provide better cycling infrastructure. We are building safe bicycle paths and comfortable bicycle bridges and tunnels. They will enable you to cycle quickly and smoothly along and across the Ring. This is how we plan to offer road users a worthy alternative to the car and to gradually reduce the number of cars on the Ring. The construction of the F23 bicycle highway is part of this ambition.

Cycling along the canal in Vilvoorde

In the future, Canal Route North (F23) will connect Boom and Brussels. The section we are building within the ‘Werken aan de Ring’ programme runs along the N260 (Brusselsesteenweg — Westvaartdijk) and will connect the Verbrande Brug in Grimbergen via Vilvoorde to the Brussels Capital Region.

  • Other cycling routes branch off at various places.
  • There are bus stops along the route and transfers to the Ringtram bus will also be possible.
  • We will be separating cyclists from the hazardous truck traffic by constructing two bicycle tunnels and a bicycle channel.
  • The planting of hedges, trees and grasses in the areas around the bicycle highway will provide a pleasant cycling experience.

Met Werken aan de Ring zetten we volop in op meer en betere fietsinfrastructuur. We bouwen veilige fietspaden en comfortabele fietsbruggen en -tunnels. Zo fiets je snel en vlot langs en over de Ring. Op deze manier bieden we weggebruikers een waardig alternatief voor de auto en verminderen we stap voor stap het aantal auto’s op de Ring. De aanleg van de fietssnelweg F23 kadert in deze ambitie.

Fietsen langs het kanaal in Vilvoorde

De Kanaalroute Noord (F23) verbindt Boom met Brussel. Het deeltraject dat we bouwen binnen het project Werken aan de Ring loopt langs de N260 (Brusselsesteenweg - Westvaartdijk) en verbindt de Verbrande Brug in Grimbergen via Vilvoorde met het Brussels Gewest.

  • Op verschillende plaatsen takken andere fietsroutes aan.
  • Langs de route zijn bushaltes en wordt aansluiting op de Ringtrambus mogelijk.
  • Dankzij de bouw van twee fietstunnels en een -sleuf scheiden we de fietsers van het gevaarlijke vrachtverkeer.
  • Het aanplanten van hagen, bomen en grassen in de zones rondom de fietssnelweg zorgt voor een aangename fietstocht.

Phasing

  • Phase 1 – Phase 2 – Phase 3

    Brusselsesteenweg from Lenterik to the industrial zone (completed)

    The renewed Chaussée de Bruxelles/Vaartdijk opened to traffic in early November 2021. The bicycle highway along the canal now separates cyclists and motorised traffic.

  • Phase 4 — Phase 5 — Phase 5b

    We have been working on the Westvaartdijk since October 2021. We are installing separated sewers, renewing the roadway and constructing more of the bicycle highway.

    The works will be progressing from north to south. We are working in several phases to ensure the accessibility of the industrial zone.

    Phase 4

    Westvaartdijk between Verbrande Brug and the Industrieweg (completed)

    The first sub-phase (Phase 4), which saw the renewal of the Westvaartdijk and Industrieweg junction, is now complete.

    Phase 5

    Westvaartdijk between the Industrieweg and the Fabrieksweg (in progress until end 2022)

    We will be working next to the industrial zone until the end of this year. Construction on the Westvaartdijk between the Industrieweg and the Fabrieksweg is ongoing. The necessary mitigation measures are being taken so that businesses can remain accessible.

    Phase 5b

    Reconstruction of the Westvaartdijk and Fabrieksweg junction (March 17th - June 2022)

    The intersection with the Fabrieksweg will be renewed from from March 17 to mid-June 2022.. Traffic will be able to pass through the works via a diversion: as there is a loop around the industrial estate, you will still be able to reach your destination.

  • Phase 6

    Westvaartdijk between the Fabrieksweg and the Verbindingsweg (august 2022 —  the end of 2022)

    From august the last part of the bicycle highway will take shape. It will connect the industrial zone and Borght. These works will be completed by the end of the year.

Cyclists

Cyclists between the viaduct and the Verbrande Brug will continue to use the cycle path that runs from the Verbindingsweg behind the industrial zone to the Humbeeksesteenweg. You can rejoin the F23 in the direction of Boom via the Verbrande Brugsesteenweg.

Motorised traffic

Between the viaduct and Borgt, you can already cycle comfortably and safely along the canal on the F23 Canal Route North cycle highway. The bicycle highway is not yet available in the Grimbergen area, as we are still laying sewers and a new roadway.

From Tuesday, 14 June onwards, traffic on a section of the Westvaartdijk will pass the work site in alternating directions. The contractor will install temporary traffic lights. This situation will continue until November this year.

Letter to the residents (in Dutch)

28 nov. '19 Grimbergsesteenweg en Vaartdijk
Pdf 72.91 kB
Download
28 nov. '19 Lenterik en Brusselsesteenweg
Pdf 346.17 kB
Download
10 aug. '19 Bewonersbrief F23
Pdf 454.93 kB
Download
9 nov '20 Bewonersbrief Laag-Kassei en Borght_0
Pdf 290.11 kB
Download
9 nov '20 Bewonersbrief Lenterik en Brusselsesteenweg_0
Pdf 281.23 kB
Download
14 dec '20 Bewonersbrief Laag-Kassei en Borght_0
Pdf 395.52 kB
Download
1 april '21 Bewonersbrief aangelanden werfzone_0
Pdf 92.86 kB
Download
6 april '21 Bewonersbrief Laag-Kassei en Borght_0
Pdf 93.67 kB
Download

Detour

28 nov. '19 F23 Fietsomleiding
Pdf 2.65 MB
Download
28 nov. '19 Adviesroute Lenterik Vilvoorde
Pdf 2.27 MB
Download

Newsletters (in Dutch)

18 dec. '19 Nieuwsbrief F23
Pdf 3.67 MB
Download
20 jan. '20 Nieuwsbrief F23
Pdf 217.41 kB
Download
6 juli '20 Nieuwsbrief F23_0
Pdf 866.49 kB
Download
15 oktober '20 Nieuwsbrief F23_0
Pdf 1.52 MB
Download
10 november '20 Nieuwsbrief F23_0
Pdf 816.8 kB
Download
16 dec '20 Nieuwsbrief F23 Kanaalroute Noord_0
Pdf 859.01 kB
Download
8 okt '21 Nieuwsbrief F23 Kanaalroute Noord_0
Pdf 1.81 MB
Download
16 dec '21 Nieuwsbrief F23 Kanaalroute Noord_0
Pdf 221.68 kB
Download
29 april '22 Nieuwsbrief Vilvoorde_1
Pdf 4.14 MB
Download
10 juni '22 Nieuwsbrief Vilvoorde_1
Pdf 4.8 MB
Download

Presentation (in Dutch)

20190827 Presentatie Vilvoorde
Pdf 7.41 MB
Download

Technical drawings

F23_Technische plannen deel1_LR_0
Pdf 20.46 MB
Download
F23_Technische plannen deel2_0_0
Pdf 15.62 MB
Download